Forum Discussion
Bert Joe Twomey
Nov 04, 2016Tin Contributor
How to get Project to assign Day Shift then Evening Shift then Night Shift
Hi All, I just joined last week - Thanks Lana at the Toronto Tech Summit I am setting up a schedule for a 24/7 job so there is: Day shift 8 am till 4 pm Even shift 4 pm to Midnight Night shift M...
WaaWaaW
Jan 20, 2021Copper Contributor
hiMehdi HAMMADI, when I do the 24 hours calendar and change the time manually to
5 pm to 12 am
12 am to 2 am
they said like this,
can u help me too?
John-project
Jan 20, 2021Silver Contributor
Try reversing your entry
12 am to 2 am
5 pm to 12 am
Some versions of Project will automatically reverse the sequence to the above even if you entered it the other way but apparently your version does not, instead it gives you an alert.
Hope this helps.
John
- WaaWaaWJan 20, 2021Copper Contributor
- John-projectJan 21, 2021Silver Contributor