Forum Discussion
Murali_krishna_P
Mar 28, 2022Copper Contributor
How to find or how do we know who deleted the projects from project center or Delete Enterprise Obje
Hi Team, we had a incident happend in the production application, that is few projects are missed We would like to know who deleted them. Is there any way to find the deleted projects? P...
Mar 28, 2022
Murali --
You would need to look at the Queue to find this information, which will tell you the Owner of the Deletion job. Hope this helps.
You would need to look at the Queue to find this information, which will tell you the Owner of the Deletion job. Hope this helps.
- Murali_krishna_PMar 28, 2022Copper ContributorThank you for reply Dale,
Can you please elobrate more on this?
what do you mean by Queue .?
Where can i find the queue list..?
Thanks,
Murali- Paul_MatherMar 28, 2022MVP
Hello Murali_krishna_P ,
If you go to PWA Settings > Manage Queue Jobs - you can check the queue jobs there.
Paul