How to enable editing project in project online when linking risks to tasks?
Hi, I'm trying to link risks with task on the project and I can't choose a task from the project because: This project can only be edited through Project Web App. Do you have any hints how I can enab...
- Mar 01, 2024
That's great to hear JoannaF , please can you mark my answer as the best response so it help others who have similar issues?
THanks
Paul_Mather
Mar 01, 2024MVP
Hello JoannaF ,
On the Enterprise Project Type (EPT) settings in PWA Admin, you will need to ensure that you sync SharePoint Tasks Lists like below:
Paul
JoannaF
Mar 01, 2024Copper Contributor
Hi Paul, I have already ticked that box but the tasks still do not appear in that list. Are there any other possibilities?
Thank you!
Thank you!
- Paul_MatherMar 01, 2024MVP
Hello JoannaF ,
Since that has been enabled, have you republished the project/s? Are the Project Sites in the main PWA site collection?
Paul
- JoannaFMar 01, 2024Copper Contributor
Hi Paul_Mather
thank you for your help! Have a nice day!
- Paul_MatherMar 01, 2024MVP
Hello JoannaF ,
Is the issue resolved?