How to edit the default.aspx page at a Project Online site?

Hey,   I am pretty sure that I had edited the default.aspx page at https://xxxx.sharepoint.com/sites/pwa/default.aspx last October. However, I realized that I cannot update this default page anymor...
  • RodFromm's avatar
    RodFromm
    Jul 05, 2024

    spoguys  You want to look a change Microsoft implemented to remove custom scripting from OneDrive and SharePoint as it may be related. You will need your Global SharePoint Admin to go M365 Message Central and review Message ID MC714186. Basically, they will need to run a PowerShell script to re-enable custom scripting on affected PWAs.  In our case, we would add new fields to a PDP then save it, but when we revisited the PDP the fields were gone.  Running the script fixed the issue.