Paolone67
Mar 19, 2021Copper Contributor
How to display Work in days within Project Center - Projects page?
Hi all, I need to show Work in Days within the Project Center view under PWA (Project Online). I found on some old TechNet forum a very old thread with the same question dated 2011 stating that t...
- Mar 19, 2021After creating the custom Project field, you need to open each project, press the F9 function key to recalculate it, then save and publish the project.
Mar 19, 2021
In addition, what formula did you create in the custom Project field? And did you use a Duration field for the formula? Please let us know and we will try to help you.
Paolone67
Mar 22, 2021Copper Contributor
Thank you very much Dale!!!
The F9 did the magic. It was the step I was missing.
Now it works. Thank you again!
- Mar 22, 2021You are more than welcome for the help, my friend!