How to display Work in days within Project Center - Projects page?
Hi all, I need to show Work in Days within the Project Center view under PWA (Project Online). I found on some old TechNet forum a very old thread with the same question dated 2011 stating that t...
- Mar 19, 2021After creating the custom Project field, you need to open each project, press the F9 function key to recalculate it, then save and publish the project.
Mar 19, 2021
Paolone67 -- By default, Duration is shown in Days and Work is shown in Hours in the Project Center page. There is no way to change this as far as I am aware. Sorry, but hope this helps.