Forum Discussion

NKumar2010's avatar
NKumar2010
Brass Contributor
Apr 22, 2022
Solved

How to display Custom column data in Gantt Chart in Project 2016 ?

Gantt chart by default displays only duration and % complete data for a task. I have created a custom Number 1 column which calculates % time elapsed and comes in decimal. I then have a Text 1 col (s...
  • John-project's avatar
    John-project
    Apr 25, 2022
    NKumar2010,
    The "Complete through" is derived from the mean duration and therefore has no relation to your custom text field for your Planned % Complete. In order to define the "From" and "To" criteria for your custom text field, you need to convert the end points of your Planned % Complete into dates in custom Start and Finish fields (e.g. Start1 and Finish1).

    John

Resources