Forum Discussion
How to display Custom column data in Gantt Chart in Project 2016 ?
- Apr 25, 2022NKumar2010,
The "Complete through" is derived from the mean duration and therefore has no relation to your custom text field for your Planned % Complete. In order to define the "From" and "To" criteria for your custom text field, you need to convert the end points of your Planned % Complete into dates in custom Start and Finish fields (e.g. Start1 and Finish1).
John
You need to create a new custom bar style that represents your custom field. Go to, Gantt Chart Format > Bar Styles group > Format > Bar Styles, and at the bottom of the list define the Name, Appearance, and other attributes of the new bar.
Understand that the priority of bar in the list of bar styles is from the bottom, that is bar styles at the bottom of the list will supersede any conflicting bars at the top of the list.
Hope this helps.
John
when I add a row at the bottom and choose a Name, Appearance etc. it overrides the appearance of existing bars displayed. It's happening probably the bottom of the list supersede bar style, as you said above.
What I'm expecting is probably two bars per task - First bar showing duration & % complete (This appears by default) and the 2nd bar showing % Planned complete. The 2nd bar is the customized bar, which I'm trying to create.
I don't know whether having two bars per task is even possible.
- John-projectApr 25, 2022Silver ContributorNKumar2010,
The Bar Styles allows up to 4 bars per task line. This is set by the "Row" in the Bar Styles window. Actually you can get even more bars by careful selection of the bar Shape.
John- NKumar2010Apr 25, 2022Brass Contributor
Thanks John.
By changing row value as 2, I am able to get the 2nd bar. But when 2nd bar appears, the length of this 2nd bar is also the same as task duration. I'd like the length of this 2nd bar (say Planned % Complete bar) to be dictated by the Planned % Column (text field) value, just like the progress bar's length is dictated by % complete.So, my Gantt chart should look like three bars
Duration bar - default, length controlled by duration field
Progress bar - default, length controlled by % complete field
Planned % complete bar - custom, length controlled by Planned % complete field.
How do I control the length of this 3rd bar ? If I select "To" as Complete Through, the length of the 3rd bar becomes equal to % complete and not Planned % Complete.
Any thoughts ?
- John-projectApr 25, 2022Silver ContributorNKumar2010,
The "Complete through" is derived from the mean duration and therefore has no relation to your custom text field for your Planned % Complete. In order to define the "From" and "To" criteria for your custom text field, you need to convert the end points of your Planned % Complete into dates in custom Start and Finish fields (e.g. Start1 and Finish1).
John