Forum Discussion

Anil_kumar's avatar
Anil_kumar
Brass Contributor
Mar 02, 2021

How to display count of baselines in project online for specific project?

Hi all,

A project have 5 baselines. Another project have 4 baselines...etc. Then how to display the baseline count for specific project by using custom filed. Any one have idea about the custom formula?

Regards,

Anil.

2 Replies

  • John-project's avatar
    John-project
    Silver Contributor

    Anil_kumar,

    Well it might be possible with a very complex custom field formula but it would be much easier with VBA.

     

    I say very complex custom field formula because it would have to utilize multiple tests to analyze every combination of the 11 Baselines along with a counter. If the baselines are always in sequence (i.e. Baseline, Baseline1, Baseline2, etc. as opposed to, Baseline, Baseline2, Baseline5, etc.) the formula would be a bit less complex but nonetheless still large. So, if the baselines are in sequence, this formula in a custom Number field will do it, at least up through Baseline5. It will be on a task by task basis but you can rollup the maximum to summary lines which will include the Project Summary Task.

    Number1=IIf([Baseline5 Start]<50000,6,IIf([Baseline4 Start]<50000,5,IIf([Baseline3 Start]<50000,4,IIf([Baseline2 Start]<50000,3,IIf([Baseline1 Start]<50000,2,IIf([Baseline Start]<50000,1,0))))))

     

    Hope this helps

     

    Oops, I didn't notice that you are using Project Online at first. I developed the formula for use with the desktop version of Project, I do not know if it will work with Project Online.

    John

    • Anil_kumar's avatar
      Anil_kumar
      Brass Contributor

      Hi John-project ,

      Thank u for your inputs......

      Yes I am using project online. So, I had searched some forums and I got this formula to get the count of baselines.

      This is the formula which I have used in project online custom filed 

      IIf([Baseline10 Finish] <> ProjDateValue("NA"), "11", IIf([Baseline9 Finish] <> ProjDateValue("NA"), "10", IIf([Baseline8 Finish] <> ProjDateValue("NA"), "9", IIf([Baseline7 Finish] <> ProjDateValue("NA"), "8", IIf([Baseline6 Finish] <> ProjDateValue("NA"), "7", IIf([Baseline5 Finish] <> ProjDateValue("NA"), "6", IIf([Baseline4 Finish] <> ProjDateValue("NA"), "5", IIf([Baseline3 Finish] <> ProjDateValue("NA"), "4", IIf([Baseline2 Finish] <> ProjDateValue("NA"), "3", IIf([Baseline1 Finish] <> ProjDateValue("NA"), "2", IIf([Baseline Finish] <> ProjDateValue("NA"), "1", IIf(IsNull([Baseline Finish]), "0", "No Value"))))))))))))