How to deal with facultative processes ?
Hi, please tell me how you work with facultative processes in MS Project ? How do you figure the prior decision in MS Project if yes or no ? Regards, mainze5
- Nov 30, 2023
Nov 28, 2023
Also, I forgot to mention that each facultative decision should be represented by a milestone task. When the decision is made, whether Yes or No, add a note to the respective milestone task to document who made the decision, the date the decision was made, the result of the decision, and why the decision was made. This way, you will have an "electronic paper trail" of each of these important decisions. Hope this helps.
mainze5
Nov 30, 2023Tin Contributor
- Nov 30, 2023mainze5 --
Wow! What a kind comment. You are more than welcome for the help, my friend!