How to customise su project group font style

I have a file with several project and I use it as synthesis of my work. I’m able to customise font style for group of actions but I don’t see how to manage subproject title. what I’m missing? tha...
  • John-project's avatar
    John-project
    May 03, 2022

    Dariocg 

    Formatting rules are different for linked structures such as a master with subprojects. The summary line insertion points, (e.g. "Subproject1"), are ignored as summary lines when using Format > Text styles. However you can use this trick. In the master, set the Marked field to "yes" for all summary lines, including subproject summary line insertion points. Then set the desired font color and style for Marked fields using Format > Text styles. This will even allow you to set the font color and style of the Project Summary Task in the master.

    John