How to customise su project group font style
- May 03, 2022
Formatting rules are different for linked structures such as a master with subprojects. The summary line insertion points, (e.g. "Subproject1"), are ignored as summary lines when using Format > Text styles. However you can use this trick. In the master, set the Marked field to "yes" for all summary lines, including subproject summary line insertion points. Then set the desired font color and style for Marked fields using Format > Text styles. This will even allow you to set the font color and style of the Project Summary Task in the master.
John
Sorry for wrong terms... I have to install English version
I have have a dynamic master with several inserted subprojects.
I'm not able to customise these titles (I.e. "Subproject1") from Format >Text style
When I say subproject title I mean the main row of a subproject in a master, the title of a subproject.
For group of actions I meant "summary tasks"
Thanks
Formatting rules are different for linked structures such as a master with subprojects. The summary line insertion points, (e.g. "Subproject1"), are ignored as summary lines when using Format > Text styles. However you can use this trick. In the master, set the Marked field to "yes" for all summary lines, including subproject summary line insertion points. Then set the desired font color and style for Marked fields using Format > Text styles. This will even allow you to set the font color and style of the Project Summary Task in the master.
John
- DariocgMay 04, 2022Tin Contributor
John-project , good idea. Thank you for your kind availability.
Hope in future Project let people set a custom conditional formatting in order to have more flexibility
- John-projectMay 05, 2022Silver ContributorDariocg,
You're welcome and thanks for the feedback.
The Marked field has been available since Project was initially released way back when (circa 1997). Personally I've never needed anything more for custom formatting but you might consider offering a suggestion via the Feedback channel in Project.
John- DariocgMay 16, 2022Tin Contributor
thank you for your suggestion of feedback. I sent a post
Just to make a sample about what I was saying, please find attached screenshot
thanks again for your kind availability
- May 04, 2022John --
Brilliant idea! I stand in awe at your ability to work around built-in behaviors in Microsoft Project. 🙂- John-projectMay 04, 2022Silver ContributorDale,
I like to "think outside the bun", like Taco Bell 😉
John