How to create cascading drop down for Project online custom fileds & lookup?
for example: country& states are 2 lookup fields if i select country as India>state filed has to show list of all states in india. if i select us>it has to show list of all states.
Jun 11, 2021
Anil -- There is no default method to do this in Project Online. A better approach, in my opinion, would be to use a single Outline Code field which would allow you to do what you want. In the Outline Code field, the first level of indent would be for the country and the second level of indent would be for the state. Hope this helps.