How to create a view to display Master projects (Parent ID) & their associated Subprojects (in POL)?
Hello, In Microsoft Project Online how can I create a view to show which of the subprojects belong to which master projects? We know how to identify a subproject and master and that the Master p...
John-project
Jun 07, 2023Silver Contributor
Noreen1590,
At master level, the subprojects are easily identified by their respective summary line insertion points. However, there is no indicator at subproject level to show what master it's inserted into.
If you have that many masters and subprojects I suggest you create a simple spreadsheet.
John
At master level, the subprojects are easily identified by their respective summary line insertion points. However, there is no indicator at subproject level to show what master it's inserted into.
If you have that many masters and subprojects I suggest you create a simple spreadsheet.
John