How to combine bucket and name in grid/timeline view?

Hi All - 

 

I am trying to combine the bucket and name column so that I can do collapse and expand. 

Below is what I am trying to achieve....

 

1 Reply

  • WendyMMU --

    I regret to tell you that this is not possible in Project for the Web. In the Timeline view, the software only displays the Name column, and it is NOT possible to add the Bucket column as well. In the Grid view, you can display the Name and Bucket columns side-by-side, but there is no way to combine them into a single value. That would require a custom field with a formula that allows you to concatenate text values, and no such field type currently exists. Sorry, but hope this helps.