How to change the default calender weekend settings
Hi how to change the default weekend and public holiday in Project Online. Thanks
niazstinu
Jan 25, 2021Brass Contributor
Thanks, Do I need to have MS Project Server to do this, as I am reading in the link you shared, that it I need to open MS Project Server and do the Enterprise calendar from there.
Currently I dont have the MS Project Server, I have only the Office 365 Project PWA.
As I read from the link you send, I need to have MS Project Server
Guillaume Rouyre
Jan 25, 2021Brass Contributor
hi niazstinu ,
No you don't need Project Server. You have PRoject Online and both work the same way for editing enterprise calendars. So the link I sent you is still applicable. But you need to have some admin rights.