Forum Discussion
JDbrasileng
Jul 08, 2023Copper Contributor
How to calculate the total delay on the programme
Please, someone could help me to calculate the actual total delay in Ms Project Professional? I have set up my baseline, updated my status date, and updated the project. But I cannot find any column...
RatanPushp
Jul 12, 2023Brass Contributor
You could calculate delay duration within a custom field. For reference, date difference formula can help in providing duration - ProjDateDiff([Finish],[Status Date]). In case, you want calculate delay based on planned / forecasted date then use "Baseline Finish" date instead of "Finish" field. Since, Status date is used in the formula, you can change Status date in Project Information section to view delays accordingly.
I hope this helps you.
- Jul 13, 2023RatanPushp --
I cannot see how your formula shows any kind of delay. Would you care to explain?