How to automatically sync availability with Project Professional?
Where exactly is your "resources calendar"? And what do you mean by "available in our company network"?
John
- AleXSR700Jan 17, 2024Copper Contributor
Well, I can share my calendar and see all calendars of my colleagues. So e.g. my calendar would be my Outlook 365 calendar. I have all my out of office and busy appointments in there.
If I am planning myself for e.g. 20 tasks, then Project will essentially plan my tasks for my earliest availability and plan 8 fulll hours per day. In reality I might have 2-3 hours per day of meetings.
As those appointments are in my calendar and they are listed as "busy" or "out of office", Project could simply exclude those times from the scheduling.
Project has this feature to add manual vacation times etc. but I would have thought that within the Office 365 package, the calendar could simply be synced so I do not have to check my and everybody else's calendar all the time.
- Jan 17, 2024AleXSR700
The feature you are seeking, which is to synchronize your resources' schedules in Microsoft Project with their Outlook calendars, does not exist. This means your only option is to manually update their calendars in the Microsoft Project file, which I know is a LOT of manual labor. Sorry, but hope this helps.- AleXSR700Jan 17, 2024Copper Contributor
Thank you for the clarification.
Do you know if Project has some kind of API that would maybe allow for PowerAutomate to enter the data into the Project file for me?
I admit that I am not a fan of PowerAutomate as it seems to be quite rudimentary in what it can do (especially compared to other flow based automations like Node-RED) but I might be willing to spend an hour or two on it if it saves me the manual labor 😉
- John-projectJan 17, 2024Silver ContributorAleXSR700,
I do not believe Project has any feature that would sync Outlook calendar for resources but I don't use Outlook so I will defer to one of my colleagues.
John- AleXSR700Jan 17, 2024Copper ContributorDo you then always manually enter every availability? Or are you using a different external calendar (instead of Outlook)?