Forum Discussion

Dariocg's avatar
Dariocg
Tin Contributor
Mar 31, 2022
Solved

How to assign resource to a specific part of a task

I have a design task with a duration of 20 weeks. During this task I need to assign: - resource A for first 5 weeks and latest 5 weeks - resource B for all these 20 weeks. Is there any way to as...
  • John-project's avatar
    Mar 31, 2022
    Dariocg,
    Yes, there are various ways to do it. Here is one:
    1. Assign both resources at 100% each via Resources > Assignments > Assign Resources
    2. Go to the Task Usage view and set the timescale for Months and Weeks
    3. Set the timescale values to zero for the 3 weeks during which resource A will not work on the task

    Hope this helps.
    John