Forum Discussion
Giuseppe1230
Oct 17, 2023Copper Contributor
How to assign hours to an activity regardless the duration
Hello everybody, I am having trouble in assigning the right amount of hours in the activities of a project I am working in. Briefly: I have task "1.1" that has lasted 20 days, and now it is 100%...
Ignacio_Martin
Oct 17, 2023Steel Contributor
Hello Giuseppe.
You can select Task type to "Fixed Duration", ... in the Advanced tab of Task Information, for example.
If you have multiple tasks created with this case, you can insert the Task Type column into the tasks table.
For future tasks, if you want them to be of the Fixed Duration Type, by default, you can set it in File > Options > Schedule > Scheduling options for this project: ...
I hope I've helped.