Forum Discussion

JBLT-77's avatar
JBLT-77
Iron Contributor
Jul 17, 2022

How Do I update Project Tasks To Reflect Actual Duration But Not Change % Complete or Actual Work

How do I update the tasks of a project to reflect actual duration (time that has passed since the task started) based on the status date, but where work on the task has not progressed from the previo...

Resources