How do I model this scenario in MS project ?
Hi, I need insights on how to model this below scenario in MS Project. I have 10 tasks; each generate a report. These 10 tasks have different durations, i.e. the reports from these tasks com...
John-project
Jan 15, 2023Silver Contributor
For your scenario you use what is called a "hammock task". This Wiki article will explain what it is and how to set it up:
https://social.technet.microsoft.com/wiki/contents/articles/32040.ms-project-hammock-tasks.aspx
John