How Do I Interpret This Overallocation in Resource Usage View
I have a project where I have 3 developers assigned to work on tasks each at 50% for a total of 150%. So I set up just a single resource and assigned the units at 150%. I assigned the resources to t...
- Jun 23, 2022John,
Glad you found the Work Availability field.
Okay, so among your three resources their total availability is 150% (max units). That translates to a total of 12h per day, or 60h per week. Any concurrent assignment over those limits will result in overallocation. Does that all make sense now?
John
Jun 21, 2022
JBLT83 --
Navigate to the Resource Sheet view in this project, and then set the Max. Units value to 300% for the RPA Developers resource. This is based on the assumption that you have three RPA developers available to work up to full-time on this project (100% x 3 developers = 300%). Reapply the Resource Usage view and now you will see the legitimate resource overallocations in your project. Hope this additional information helps.
Navigate to the Resource Sheet view in this project, and then set the Max. Units value to 300% for the RPA Developers resource. This is based on the assumption that you have three RPA developers available to work up to full-time on this project (100% x 3 developers = 300%). Reapply the Resource Usage view and now you will see the legitimate resource overallocations in your project. Hope this additional information helps.