Forum Discussion

JBLT-77's avatar
JBLT-77
Iron Contributor
Jun 20, 2022

How Do I Interpret This Overallocation in Resource Usage View

I have a project where I have 3 developers assigned to work on tasks each at 50% for a total of 150%. So I set up just a single resource and assigned the units at 150%.  I assigned the resources to t...
  • John-project's avatar
    John-project
    Jun 23, 2022
    John,
    Glad you found the Work Availability field.

    Okay, so among your three resources their total availability is 150% (max units). That translates to a total of 12h per day, or 60h per week. Any concurrent assignment over those limits will result in overallocation. Does that all make sense now?

    John

Resources