How do I bulk modify priority for multiple tasks simultaneously?
How do I enter similar task information for multiple tasks simultaneously? I tried following these instructions on the MS support site, but the task information didn't get updated with the new inform...
Eric2350
Nov 27, 2022Former Employee
Thanks John-project for the quick reply.
If you compare the columns in the 1st step's snapshot with the 4th step's snapshot, you can see that the 6th column is the priority value and it is unchanged.
That's interesting that it works for you but not for me. I wonder if it has something to do with the different version I'm using.
John-project
Nov 27, 2022Silver Contributor
Eric2350,
Sorry, I didn't see the Priority field in your screen shots. My eyes ain't what they used to be 😞
It could very well be due the 22H2 update, I recently saw another post (unrelated issue) where the user had the 22H2 update. Since you're using Project Online I don't think you can "back out" of the update but perhaps colleagues Paul or Dale have more insight on that update and will check in to this thread.
John
John
Sorry, I didn't see the Priority field in your screen shots. My eyes ain't what they used to be 😞
It could very well be due the 22H2 update, I recently saw another post (unrelated issue) where the user had the 22H2 update. Since you're using Project Online I don't think you can "back out" of the update but perhaps colleagues Paul or Dale have more insight on that update and will check in to this thread.
John
John
- Eric2350Nov 27, 2022Former Employee
Thanks, John-project.
I'd like to just clarify that I'm using an "on-premises" version of MS Project (meaning it's installed on my computer and I don't have to log into a website).