How can I modify a task in Project for the web by Power Automate
Hi all I would like to find a way to modify a task as change start date, change finish date, or change duration in a task in Project for the web by Power Automate. regards Truong Dai.
Chibo1215
Dec 23, 2022Copper Contributor
daibt Thank you, this lead me to a solution. I was able to change the dates on a task using Power Automate by using the msdyn_PSSUpdateV1 API.
https://learn.microsoft.com/en-us/dynamics365/project-operations/project-management/schedule-api-preview?source=recommendations
daibt
Dec 27, 2022Brass Contributor
Chibo1215 thánks you so much
This is a Project Operations document, not for Project for the Web. You can test other activities like creating a new task, changing the duration. Hope we have a good solution for P4W
Let me ask one more question, can we use HTTP, or HTTPS, as documented here https://learn.microsoft.com/en-us/azure/connectors/connectors-native-http
- Chibo1215Dec 27, 2022Copper ContributorThis blogpost was helpful for me.
https://daytodaydynamics365.com/project-operations-and-project-for-the-web-schedule-api-guide-for-power-automate-users/