How can I create Grouping by Text Field in MS Project?
- Sep 03, 2021
Okay, then why not simply sort by Outline Level. This structure:
Gives this result:
If that doesn't work for you (i.e. you really, really, really need the grouping format), then it can be done with something like this:
But if you absolutely just have to have a pure grouping format of the Text1 (e.g. WBS) field, then that can be done with some VBA.
Wow, so many options. I'm sure your head is spinning.
John
But I can't group hierarchycally as I show on my screenshot. If I select Group by Text1, I have only ascending grouping.
Is it possible in MS Project. If not, please write about it.
BR, Vasily
Okay, then why not simply sort by Outline Level. This structure:
Gives this result:
If that doesn't work for you (i.e. you really, really, really need the grouping format), then it can be done with something like this:
But if you absolutely just have to have a pure grouping format of the Text1 (e.g. WBS) field, then that can be done with some VBA.
Wow, so many options. I'm sure your head is spinning.
John