Forum Discussion
JBLT-77
Aug 18, 2022Iron Contributor
How Can I Apply Both A Filter and Highlight in a View
I have a view set up with the Incomplete Tasks filter applied. I also want to then highlight slipping tasks by applying the Slipping highlight option. It appears however that project doesn't let yo...
- Aug 18, 2022JBLT83 --
Yes, you are correct that you can only apply one filter at a time. And you are correct that you would need to either edit the Slipping Tasks filter to eliminate completed tasks, or you would need to create a new filter for this purpose. Hope this helps.
JBLT-77
Aug 18, 2022Iron Contributor
Dale_HowardMVP Bummer. I'll have to make a feature suggestion to microsoft that they'll probably never implement. So there's no workaround huh.
John-project
Aug 18, 2022Silver Contributor
John,
My comment from the peanut gallery; Dale did give you a workaround, edit the existing filter or create a new filter to do what you need.
John
My comment from the peanut gallery; Dale did give you a workaround, edit the existing filter or create a new filter to do what you need.
John