Forum Discussion
Gongi1625
Sep 11, 2024Copper Contributor
History export
Hi, I’m trying to create a report in Power BI or Excel with the history of tasks for the entire project. We have options to track the history of each task, but I would like to see the history as one...
RodFromm
Sep 12, 2024Steel Contributor
Gongi1625 Here is another option, if you can publish your data to a Power BI Premium Workspace and have Power Automate. In the workspace, create a paginated report and using Power Automate write the require data (fields) to a file, or directly to a dataverse table. The flow can be scheduled to run on daily, weekly, etc., or as needed. You would then pull this data into your Power BI model and assign the appropriate relationships. You would also need to establish some processes to validate the stored data as projects and tasks may get deleted over time and you need to determine how you want to handle those situations.