Historic RAG
Hi,
This might not be a solution for you but as we had the same use case I made following process as a workaround and thought to share it with you in case it helps:
1. A custom list in Project Site (SharePoint) created.
2. on each reporting round (weekly or monthly, etc) a new item created. We have status commentary beside the RAG status for each project.
3. in reporting solution (in our case: Power BI) we pull all the items from that custom list and then we can review history of RAG changes.
PS: as you rightfully mentioned currently the RAG field in Project Online doesn't keep the history.
Regards,
Naser
- pauleastDec 09, 2019Copper Contributor
Hi Naaser
Is that automated? We have 50+ projects to monitor do you use a single line for each project each month?
Thanks
Paul
- NaaserDec 09, 2019Copper Contributor
Hi Paul,
The status of each project is independent, therefore we have each project has its own list of status and RAG list which get updated with the its project manager on weekly basis.
Also remember that project site (SharePoint site) is dedicated to each project in Project Online environment.
I am not sure what do you mean with automation; the updates are done by project managers manually and the report is automatically populated in Power BI. This is overall project health which is based on all aspects of the projects. we have other RAGs like cost or schedule and etc. which is rule based.
Regards,
Naser