Highlight tasks ahead of schedule
Hi, We have a programme created in Project, we have applied a progress line which shows when we are on or behind schedule, but there are a few tasks where we are head of schedule - is there a wa...
PlannersPlace
Nov 24, 2023Brass Contributor
I've got a https://youtu.be/dxsp6x9dD98 on highlighting late tasks using bar styles, which you can adapt to show tasks that are ahead of schedule.
Alternatively, you can set-up a Custom Flag field to display a green icon using the formula IIf( [Finish Variance]< 0,Yes ,No)