Forum Discussion
RobertOrnelas
Feb 12, 2024Iron Contributor
Hide Grouping titles and header names
Is it possible to hide Group headers/titles? For example, I want to see the project name, but I don't need to see the word "Project" before every project. I know it's a Project, and it's just wasti...
- Feb 14, 2024
Hello, Robert.
Unfortunately your grouping fields are not Lookup (List) type, but if you have a exceptional need and want to try:
- Create 2 custom text fields Lookup type(Custom attributes in the form)
- Select the option "Allow additional items to be entered into the fields"(into Lookup Table)
- Close
- Copy and paste Project and Resource Initials columns into the new custom fields respectively
- Group finally by these two Lookup fieldsIt is a momentary solution for an emergency.
Ignacio
Feb 13, 2024
Robert --
I just figured out what you are showing in your screenshot. It appears to be a master project in which you have applied Grouping by Project at the first level and then Grouping by Resource Initials at the second level. The default behavior of grouping is that each group shows the field on which you are grouping, following by the data in that field. So, you either need to live with the word Project appearing for every project, or you need to remove the grouping. Sorry, but hope this helps.
I just figured out what you are showing in your screenshot. It appears to be a master project in which you have applied Grouping by Project at the first level and then Grouping by Resource Initials at the second level. The default behavior of grouping is that each group shows the field on which you are grouping, following by the data in that field. So, you either need to live with the word Project appearing for every project, or you need to remove the grouping. Sorry, but hope this helps.