Forum Discussion

chinthala91's avatar
chinthala91
Copper Contributor
Jun 17, 2024

hi i am having some issue in MS project progress update of fixed duration task

in the above schedule task-6 slab formwork is started before the predecessor task has finished. say it started on 05-06-2024 and i am updating the progress on end of 12th day i.e 16-06-2024. so...

Resources