Forum Discussion
azrenmohamed
Aug 30, 2024Copper Contributor
help newbie in microsoft project
i need to update my project, using already make template. when i update the predecessor, my date didn't change. anyone know why? i suspect this template is locked (maybe). anyone can help me?
John-project
Aug 30, 2024Silver Contributor
azrenmohamed,
What version of Project are you using? What template are you using and where did you get it?
Does the Project header say the template name with a "read only"?
What do you mean by "update the predecessor"? What exactly are you trying to update?
John
What version of Project are you using? What template are you using and where did you get it?
Does the Project header say the template name with a "read only"?
What do you mean by "update the predecessor"? What exactly are you trying to update?
John
- azrenmohamedSep 01, 2024Copper Contributor
long story is, i am a sub-contractor. the m.project file i got from main contractor. i need to do scheduling based on main contractor progress work. so i add my task on main contractor m.project file. when i want to update the predecessor (based on main contractor progress), my task's date didn't update as the predecessor task i set.
- John-projectSep 02, 2024Silver Contributor
Unfortunately your "long story" didn't answer any of my, or Dale's, questions. What version of Project are you using? Are the tasks manually scheduled and if so, why? How exactly are you updating progress?
And a couple more questions to be answered. Is calculation set to "on"? Do the tasks have constraints?
A screen shot would help.
John