Forum Discussion
JBLT-77
Aug 02, 2022Iron Contributor
Help Creating Custom Field to Calculate Elapsed Duration to Compare Against Actual Work Duration
I created a custom text field called Elapsed Duration as I want to use this field instead of the built-in "Actual Duration" field which calculates based on % complete. I want to monitor and know the ...
John-project
Aug 17, 2022Silver Contributor
John,
I question what kind of plan you have if most of your tasks don't have dependencies. Not even the normal finish-to-start?
Anyway, I think we've run this topic to the ground. If you got something you like, right or wrong, go with it.
John
I question what kind of plan you have if most of your tasks don't have dependencies. Not even the normal finish-to-start?
Anyway, I think we've run this topic to the ground. If you got something you like, right or wrong, go with it.
John
JBLT-77
Aug 18, 2022Iron Contributor
John-project In agile projects tasks/aka requirements/aka user stories are supposed to be Independent, meaning it shouldn’t have any predecessors or successors. However in practice it’s not always possible to meet the I-Independent for the story INVEST criteria. Some requirements have to be implemented before others but not all. When these instances occur then I establish the predecessor in project and JIRA has an option to select must be done before or must be done after and then you link it to the related requirement/story