Help Creating Custom Field to Calculate Elapsed Duration to Compare Against Actual Work Duration
You are definitely right, it gets complicated.
Again I reiterate, there is no relationship between Actual Duration and the Status Date, so other than using your "fudge" factor ( "iif" statement to tweak the results) you will never get Actual Duration to mold to what you want (i.e. you will never "solve for that").
Maybe you can simply things. How about you define the total duration (i.e. when task should start to when it should finish) as Baseline Duration plus and lags (if present). It includes wait times plus in-process work time. Then work duration is actual start to actual finish or actual start to status date, whichever applies.
Straightforward with no fudge factors needed.
John
John-project So I ended up using the workaround where if the actual duration is greater than elapsed duration it sets the work duration value equal to the elapsed duration. I don't think using baseline fields would be good because that's according to the "Plan", not what actually happens. in measuring process performance, I need "Actuals". As far as lags, I've never had the need to use lags in an agile project. Most of my project tasks don't have predecessors/dependencies. So, I don't see how lags would be applicable here.
I'm just going to stick with my Work Duration formula that uses actual duration with the condition that work duration can't exceed elapsed duration. It may not be precise, but I think it will be good enough to measure work efficiency.
- JBLT-77Aug 18, 2022Iron Contributor
John-project In agile projects tasks/aka requirements/aka user stories are supposed to be Independent, meaning it shouldn’t have any predecessors or successors. However in practice it’s not always possible to meet the I-Independent for the story INVEST criteria. Some requirements have to be implemented before others but not all. When these instances occur then I establish the predecessor in project and JIRA has an option to select must be done before or must be done after and then you link it to the related requirement/story
- John-projectAug 17, 2022Silver ContributorJohn,
I question what kind of plan you have if most of your tasks don't have dependencies. Not even the normal finish-to-start?
Anyway, I think we've run this topic to the ground. If you got something you like, right or wrong, go with it.
John