Forum Discussion
JBLT-77
Aug 02, 2022Iron Contributor
Help Creating Custom Field to Calculate Elapsed Duration to Compare Against Actual Work Duration
I created a custom text field called Elapsed Duration as I want to use this field instead of the built-in "Actual Duration" field which calculates based on % complete. I want to monitor and know the ...
ignacio_martin_mvp
Aug 02, 2022Copper Contributor
Hi Juan
You can try the following formula, in a custom duration field, such as Duration1, for example:
IIf([Actual Finish]<[Status Date];round(ProjDateDiff([Actual Start];[Actual Finish])/480)*480;IIf([Actual Start]<[Status Date];round(ProjDateDiff([Actual Start];[Status Date])/480)*480;0))
Regards
You can try the following formula, in a custom duration field, such as Duration1, for example:
IIf([Actual Finish]<[Status Date];round(ProjDateDiff([Actual Start];[Actual Finish])/480)*480;IIf([Actual Start]<[Status Date];round(ProjDateDiff([Actual Start];[Status Date])/480)*480;0))
Regards
JBLT-77
Aug 03, 2022Iron Contributor
ignacio_martin_mvp Yes, I believe this formula works. I got a syntax error at first because you used semi colons in the formula so I had to replace those with commas. I can now see that a tasks baseline duration was supposed to be 20 days and is 25% complete, however the actual elapsed duration or time its been in an In Progress status shows 36 days. Thank you for your help.