Forum Discussion
JBLT-77
Aug 02, 2022Iron Contributor
Help Creating Custom Field to Calculate Elapsed Duration to Compare Against Actual Work Duration
I created a custom text field called Elapsed Duration as I want to use this field instead of the built-in "Actual Duration" field which calculates based on % complete. I want to monitor and know the ...
JBLT-77
Aug 02, 2022Iron Contributor
This was my first attempt to build nested custom field functions, but its generating a #ERROR
IIf([Actual Duration]=0,"NA",IIf([Actual Duration]>0,ProjDateDiff([Actual Start],[Actual Finish])/480 & " " & "d",ProjDateDiff([Actual Start],[Status Date])/480 & " " & "d"))
IIf([Actual Duration]=0,"NA",IIf([Actual Duration]>0,ProjDateDiff([Actual Start],[Actual Finish])/480 & " " & "d",ProjDateDiff([Actual Start],[Status Date])/480 & " " & "d"))