Forum Discussion
JBLT-77
Aug 06, 2022Iron Contributor
Handling Baselines In Project When Deleting a Task
I removed a couple tasks from my MS Project plan, and then started to wonder if by deleting the task, that project would automatically adjust the baseline, but I don't think that's the case, is it? ...
Aug 06, 2022
JBLT83 --
I strongly recommend that you cancel unneeded tasks that have been baselined, rather than deleting them. Refer to the following blog post article I wrote on this exact subject:
https://www.projility.com/cancel-an-unneeded-task/
Hope this helps.
I strongly recommend that you cancel unneeded tasks that have been baselined, rather than deleting them. Refer to the following blog post article I wrote on this exact subject:
https://www.projility.com/cancel-an-unneeded-task/
Hope this helps.
JBLT-77
Aug 06, 2022Iron Contributor
Dale_HowardMVP Unfortunately I'm using project standard so I can't inactivate a task by simply checking a box. The steps for project standard seem too cumbersome.