Granting users access to view the Project Schedule within Project Online
We have users that are part of a project team but may not necessarily be assigned tasks on the plan. How can we grant them access to view the project schedule from within Project Online? I'm talking a...
Paul_Mather
Sep 10, 2021MVP
Hello John Passaro ,
This will depend on the Permission mode your PWA site in using. If in the Project Permission mode you can use the direct Project Permissions as seen below:
Or you can update the Project permission model in the PWA Settings page.
You can check the permission mode used in the PWA settings --> Advanced Server Settings:
If in the SharePoint permission mode you would need to add them to another permission group but that would give them access to more projects that just the one.
Many thanks
Paul