Forum Discussion
Fadyef
Sep 27, 2022Copper Contributor
Grant access to project resources on the SharePoint site associated to the project
Hi, How can I grant access automatically to project resources on the SharePoint site associated to an Enterprise project (created automatically during Enterprise project creation). NB: permissio...
- Sep 27, 2022Fady --
First of all, you need to change your PWA to Project Permissions Mode, which will provide the permissions granularity that you need. Once you have done this, Project Web App will grant SharePoint permissions to users as follows:
1. The Project Manager of a published project will have full access to the SharePoint site for the project.
2. Team members that are assigned to tasks in a published project will have Read/Write access to all objects in the SharePoint site for that project.
3. Executives will have View-Only access to the objects in the SharePoint site for every project.
Hope this helps.
Paul_Mather
Sep 27, 2022MVP
Hello Fadyef ,
Following on from Dale's great advice, you will also need to ensure that the "Sync User Permissions" is also enabled on the EPT settings as seen below:
Note that the user permissions are only synchronised for projects sites created inside the Project Web App site collection.
Paul
Sep 28, 2022
Good catch, Paul!