Grant access to project resources on the SharePoint site associated to the project

Hi, How can I grant access automatically to project resources on the SharePoint site associated to an Enterprise project (created automatically during Enterprise project creation).   NB: permissio...
  • Dale_HowardMVP's avatar
    Sep 27, 2022
    Fady --

    First of all, you need to change your PWA to Project Permissions Mode, which will provide the permissions granularity that you need. Once you have done this, Project Web App will grant SharePoint permissions to users as follows:

    1. The Project Manager of a published project will have full access to the SharePoint site for the project.

    2. Team members that are assigned to tasks in a published project will have Read/Write access to all objects in the SharePoint site for that project.

    3. Executives will have View-Only access to the objects in the SharePoint site for every project.

    Hope this helps.