Ghant Chart - Status date line

Good day, How do I , can I put a date on the Status date line in the Ghant chart? 
  • Ignacio_Martin's avatar
    Jul 02, 2024

    Hi JeanineB007 

     

    I don't think there is a direct option to display a label with the Status Date. But you can try to draw a box and insert some text in the Gantt, and write the status date manually, in Gantt Chart Format > Drawings > Text Box,... and double click on the box to edit the format.

     

    Ignacio