Forum Discussion
JeanineB007
Jul 02, 2024Copper Contributor
Ghant Chart - Status date line
Good day, How do I , can I put a date on the Status date line in the Ghant chart?
- Jul 02, 2024
Hi JeanineB007
I don't think there is a direct option to display a label with the Status Date. But you can try to draw a box and insert some text in the Gantt, and write the status date manually, in Gantt Chart Format > Drawings > Text Box,... and double click on the box to edit the format.
Ignacio
Ignacio_Martin
Jul 02, 2024Steel Contributor
Hi JeanineB007
I don't think there is a direct option to display a label with the Status Date. But you can try to draw a box and insert some text in the Gantt, and write the status date manually, in Gantt Chart Format > Drawings > Text Box,... and double click on the box to edit the format.
Ignacio
- JeanineB007Jul 02, 2024Copper ContributorThank you, thought might be that. perfect thanks