Forum Discussion
Getting Work Contour in Project for the Web
Hi
In Project for the Web, the new Assignments view has been released recently. We would like to get to that data for reporting, for heatmaps and other reports.
I've figured out that the Project for the Web schedule page reads from the PSS API using this call to actually read it: /pss/api/v1.0/projects(projectid)/assignments/?$select=taskId,percentWorkComplete,resourceId,work,start,finish,totalWorkContour&$startDate=2022-12-01T00:00:00.000Z&$endDate=2022-12-08T00:00:00.000Z&$segmentLengthInHours=24
It uses updateWorkContour to then update. I've found msdyn_UpdateAssignmentEffortContour in the Resource Assignments bound actions in Power Automate, and msdyn_PssUpdateResourceAssignmentContourV1 in the unbound actions.
Of course, those don't help me, because I need to know what the current values are before trying to update them, or what I actually want to do to which is report.
We initially thought that the data is stored on the msdyn_resourceassignment table, in msdyn_plannedwork, but realised that it only stores Remaining Work, once you start changing the progress on the assignment the completed days goes away.
Does anyone know if there's a way to read the data using the DataVerse API? There's nothing I can find in the CSDL $metadata either
11 Replies
- anbemo0Copper Contributor
Hello Everyone, has anyone found where Microsoft saves this information? Thanks.
- DuncanGriffinBrass Contributor
Hi Mandarb565
This planned work information is included in the updated version of the Power BI reports included within the Project Accelerator up on https://github.com/OfficeDev/Project-Accelerator
There is a table called "Resource Timephase" which breaks resource demand into day records. If you add a custom day-to-day table( eg. DayByDay = Calendar("01/01/2021","01/01/2024") ) and create a relationship back to the "Resource Timephase" table you can then build out your own resource demand reports.
Hope this helps.
- Mandarb565Copper Contributor
Thank you for the reply,
That's the msdyn_plannedwork column I mentioned. It effectively shows only Remaining Work once you change the effort complete or percentage complete. As an example, the below task I had 40 hours assigned. The left hand side is the planned work column before I changed the percentage to 25%. The first two days are removed, shown in red on the right hand side.
This works for some reports, but not for everything we need.- Mandarb565Copper Contributor
Oh, and the Assignment view keeps that data