Forum Discussion
Getting values of "start" and "end" for a summary task
- Mar 01, 2023gautiercoadou,
Thanks for the screen shot. It allowed me to understand and determine what is wrong. I think the issue is a simple matter of you forgetting to check the box to use the formula for "calculations for task and group summary rows" for your custom date field "Copie ? fin".
John
First of all thanks for you answer
I use Project desktop version 2301 build 16026.20200
Below you can see a printscreen
A littrle bit of explanations here
"Début" means "start",
"Fin" means "End"
"Copie ? début" is a date-type custom fiels with a formula [Copie ? début] = [début]
"Copie ? fin is a date-type custom fiels with a formula [Copie ? fin] = [fin]
I also tried with start-type custom field but it still didn't work
As you can see, fo my summary task Marché GOF
the value of "Copie ? début " should be 27-02-23, and i get "03-02-20"
the value of "Copie ? début " should be 06-07-23, and i get "NC"
Regards
You missed one step in creating the formula in each of these two custom fields. In the Custom Fields dialog, select one of the fields containing the formula and then select the Use Formula option in the middle of the dialog, such as shown below. Do the same for the other formula as well. Your formula should now work correctly in both of the custom fields. Hope this helps.