Forum Discussion
CSchreiber
Jun 21, 2022Copper Contributor
Gantt for specific resourced tasks
Still struggling with this ... Is it possible to show and print a Gantt of tasks associated with a specific resource?? I would like to do this from a master schedule. For example, I would like to s...
- Jun 22, 2022Cschreiber --
In a master project, the dialog does not show a drop down list. You have to type the name of the resource whose tasks you want to see. It is an oddity of master projects. Try typing a resource name and then confirm whether the filter works or not, and then let us know.
CSchreiber
Jun 21, 2022Copper Contributor
Dale,
Thanks sooo much for your help. I feel I'm getting closer. I have not been able to get the resourced tasks from the Master Schedule, but I can with each sub-project schedule. I noticed when I'm in the Master schedule, the Resources Usage filter does not provide a drop down list, however, in the sub project schedules it does. I believe this means the requested filter view isn't communicating with the resource sheet, I think??
Do you have any idea what's gone wrong? I have a feeling it may be an ID-10-T error, LOL!
Thanks sooo much for your help. I feel I'm getting closer. I have not been able to get the resourced tasks from the Master Schedule, but I can with each sub-project schedule. I noticed when I'm in the Master schedule, the Resources Usage filter does not provide a drop down list, however, in the sub project schedules it does. I believe this means the requested filter view isn't communicating with the resource sheet, I think??
Do you have any idea what's gone wrong? I have a feeling it may be an ID-10-T error, LOL!
John-project
Jun 22, 2022Silver Contributor
CSchreiber,
If I may step in. The reason you don't see the drop down when using the "Using Resource" filter at master level is because there are no resources in the master, so there's nothing to "drop down".
John
If I may step in. The reason you don't see the drop down when using the "Using Resource" filter at master level is because there are no resources in the master, so there's nothing to "drop down".
John