Gantt for specific resourced tasks

Still struggling with this ... Is it possible to show and print a Gantt of tasks associated with a specific resource?? I would like to do this from a master schedule.  For example, I would like to s...
  • Dale_HowardMVP's avatar
    Dale_HowardMVP
    Jun 22, 2022
    Cschreiber --

    In a master project, the dialog does not show a drop down list. You have to type the name of the resource whose tasks you want to see. It is an oddity of master projects. Try typing a resource name and then confirm whether the filter works or not, and then let us know.