Gantt Chart View does not show all the project names next to the Gantt Chart bars
Hi everyone, see picture above for reference. I am having struggles with formatting my Gantt Chart. I want all the project names to show up next to the Gantt bars. For some reason, only som...
- Jan 12, 2023
Check that your Bar Styles Text is set for Task and Manual Task bars.
Your screenshot is for Critical bar but would be good to see Task & Manual Task
Hatem789
Jan 12, 2023Copper Contributor
I tried that but it still does not work unfortunately
PlannersPlace
Jan 12, 2023Brass Contributor
add a screenshot of the bar styles with Text tab selected
- Hatem789Jan 12, 2023Copper Contributor
- PlannersPlaceJan 12, 2023Brass Contributor
Check that your Bar Styles Text is set for Task and Manual Task bars.
Your screenshot is for Critical bar but would be good to see Task & Manual Task
- Hatem789Jan 12, 2023Copper Contributorthat solved it! It was the "Manual Task" that was set incorrectly. Thank you so much for pointing that out