Forum Discussion

Hatem789's avatar
Hatem789
Copper Contributor
Jan 12, 2023
Solved

Gantt Chart View does not show all the project names next to the Gantt Chart bars

Hi everyone, see picture above for reference.   I am having struggles with formatting my Gantt Chart. I want all the project names to show up next to the Gantt bars. For some reason, only som...
  • PlannersPlace's avatar
    PlannersPlace
    Jan 12, 2023

    Hatem789 

     

    Check that your Bar Styles Text is set for Task and Manual Task bars.

     

    Your screenshot is for Critical bar but would be good to see TaskManual Task

Resources